Extreme wind values - 35 years of reanalysis
GEV fit on annual wind maxima (ERA5, 1990-2024) off Ushant: return levels and bootstrap confidence interval, the basis of any design study.
Context
An offshore structure is designed against rare events. The 50-year value is the level exceeded on average once every 50 years, a probability of about 2% each year. It is almost never observed directly: it has to be estimated by extrapolation, and its uncertainty stated.
Data and method
- Record: the 35 annual maxima of 10 m wind speed, from 1990 to 2024, from the ERA5 reanalysis through Open-Meteo, off Ushant.
- Fit: a GEV (Generalized Extreme Value) distribution, suited to block maxima.
- Uncertainty: 90% confidence interval by bootstrap (500 resamples of the record).
Results
- 10-year value: 25.0 m/s (90% interval: 23.4 to 26.5 m/s).
- 50-year value: 28.4 m/s (interval: 24.5 to 33.7 m/s).
- 100-year value: 30.0 m/s (interval: 24.8 to 37.9 m/s).
- The 35 observed annual maxima range from 19.2 to 33.6 m/s.
Reading
The key reading is not the central value but the interval: at 50 years it spans more than 9 m/s, and it widens with the return period because 35 observations contain few rare events. The highest observed maximum (33.6 m/s) sits at the top of the 50-year interval. This is the uncertainty a design must state explicitly.
This analysis is a demonstration on public data: a reanalysis smooths the peaks, and a design criterion would require correcting its biases against measurements.